The Siemens SGT68000H is a highperformance gas turbine, designed for combined cycle efficiencies of 61%. Short installation times are achieved by a special focus on site assembly. Package subsystems are modularized and installed in auxiliary packages in order to minimize field assembly.
In 16 weeks, the entire GT package is constructed. In only five months, the SGT68000H is ready for operation.