What are Project Planning and Scheduling checks before submission of Baseline to Client

Follow
Learn with EngrWaqas

For More Details to Enroll for our
✅ Upcoming Live Webinar
✅Career Counselling Sessions for Engineering Community
✅ Job hunting in Gulf region
✅ Primavera p6 Training Sessions

Whatsapp ✅ +92 312 6866126 ✅ +92 336 92 57657 Primavera P6 is a widely used project management software that helps in project planning, scheduling, and management. When using Primavera P6 for project management, there are specific checks and steps to consider before submitting a baseline to the client:

Data Accuracy and Integrity:

Verify that all project data, including activities, resources, durations, and constraints, are accurate and up to date in the Primavera P6 database.
Project Schedule Review:

Review the entire project schedule to ensure it reflects the latest project plan and scope.
Check that all activities are correctly sequenced with appropriate dependencies.
Validate that milestones and deliverables are clearly defined and logically linked to the schedule.
Resource Allocation:

Confirm that resources are properly allocated to activities and are not overallocated.
Ensure that resource assignments align with the project plan and are within resource availability limits.
Critical Path Analysis:

Analyze the critical path to identify any critical activities and understand their impact on the project timeline.
Verify that any changes to critical activities are welldocumented and communicated.
Constraints and Deadlines:

Review constraints and deadlines to ensure they are accurately represented in the schedule.
Check for any constraints that may affect the project's flexibility.

For Live webinar or Full Training whatspp +92 311 4396983
www.theskillsage.com

Resource Loading:

Examine resource loading to ensure that resource assignments are balanced and within capacity.
Address any resource overallocations or bottlenecks.
Cost Estimates:

Validate cost estimates in the schedule to ensure they align with the project budget.
Verify that cost data is correctly allocated to activities and resources.
Risk Assessment:

Ensure that risk assessments and mitigation strategies are integrated into the schedule.
Check that contingency plans for highimpact risks are in place.
Quality Assurance Plan:

Confirm that the quality assurance plan is reflected in the schedule, indicating when quality checks and reviews will take place.
ClientSpecific Requirements:

Tailor the schedule to meet any specific requirements or preferences of the client.
Ensure that the schedule format and presentation align with the client's expectations.
Baseline Creation:

Generate the baseline in Primavera P6, which serves as a snapshot of the project schedule at a specific point in time.
Verify that the baseline accurately represents the approved project plan.
Documentation:

Ensure that all project planning documents, including the baseline schedule, are properly organized and documented.
Save backup copies of the baseline schedule for reference.
Client Approval:

Seek client approval or input on the baseline schedule before final submission.
Address any client concerns or revisions promptly.
Communication Plan:

Confirm that the project's communication plan is in place and includes regular updates to the client on project progress and changes.
Legal and Contractual Compliance:

Ensure that the project schedule aligns with all legal and contractual obligations specified in the project contract.
Stakeholder Alignment:

Verify that all key stakeholders, both internal and external, are aligned with the baseline schedule and have signed off on it if required.
Contingency Plans:

Have contingency plans in place for managing unexpected issues or delays during project execution.

By conducting these checks in Primavera P6 before submitting the baseline to the client, you can help ensure that the project schedule accurately represents the project plan and that it meets the client's expectations and requirements. This can contribute to successful project execution and client satisfaction.

Useful Primavera p6 Tutorials
   • Mastering Primavera P6 UserDefined F...  
   • How to Develop S curve or Cash Flow i...  
   • Planning Engineer Session of Enrolled...  
   • 5 Skills set you must know If you are...  

#ProjectPlanning
#ProjectScheduling
#PrimaveraP6
#BaselineSubmission
#ScopeValidation
#ScheduleAccuracy
#ResourceAllocation
#CriticalPathAnalysis
#Constraints
#ResourceLoading
#CostEstimates
#RiskAssessment
#QualityAssurance
#ClientApproval
#CommunicationPlan
#StakeholderAlignment
#ContingencyPlans
#LegalCompliance
#ContractualRequirements
#Milestones
#Deliverables
#ChangeManagement
#ProjectManagement
#ProjectBaseline
#ProjectDocumentation
#ProjectExecution
#ClientExpectations
#ProjectContract
#ProjectProgress
#ClientSatisfaction

posted by negreanbl